Zones and conduits: start from the risk, not from the switch
Segmentation projects usually start with a list of switches and a wish to get rid of a few flat VLANs. That is a network project. A security project starts one step earlier, with a question that has nothing to do with hardware: what happens to the product, the people and the plant if this group of assets is compromised?
The difference shows a year later. A network-first design produces a tidy diagram, and when someone asks why the packaging line and the utilities share a zone, the only answer is that they shared a switch. A risk-first design can answer that question for every boundary on the drawing.
How we run it
A workable zone model comes out of four passes over the same installed base.
- Inventory. Every asset, including the ones nobody maintains: the vendor PC under the conveyor, the old HMI that still talks to the historian, the wireless bridge someone added to reach the warehouse.
- Consequence. What each asset can do to the product, to safety and to availability if it misbehaves or is taken over.
- Grouping. Assets that share a consequence and a level of trust become a candidate zone.
- Target. Each zone gets a target security level, and each path between zones becomes a conduit with its own requirements.
Only then does the network design start, and by that point most of it has been decided. IEC 62443-3-2, the part of the series that deals with risk assessment for system design, follows the same order: define the system under consideration, assess the initial risk, partition it into zones and conduits, then carry out a detailed risk assessment that sets a target security level for each zone. The switches come afterwards.
What usually comes out of the workshops
The first surprise is almost always the inventory. On a typical site the walk-down finds assets that are on no drawing, and connections that were made for a commissioning and never removed. The second surprise is that the consequence pass regroups things engineering had kept apart, and splits things IT had kept together. A process skid and its local HMI belong together; the same skid and the office printer on the next floor do not, even if they share a VLAN today.
The workshops work best with three people in the room who rarely sit together: the process or production engineer who knows the consequences, the automation engineer who knows the systems, and the network or IT person who will build the result. Two half-day sessions per production area is a realistic pace.
Legacy assets are the test
Every site has a PLC that cannot authenticate, cannot be patched and cannot be replaced before the next major shutdown. The 62443 series has an answer for it: the asset goes into a zone of its own, behind a device that enforces the conduit, and a compensating countermeasure covers what the controller cannot do itself, with the reason written down. What it must never become is an exception nobody recorded.
Recording it is the whole point. A documented exception has an owner, a review date and a risk someone accepted. An undocumented one is a hole in the model that the next engineer will not know about.
What the zone model is really for
The drawing is a by-product. What the model gives you is a list of decisions you can defend: why this zone, why this boundary, why this exception, who agreed. That list is what an auditor asks for, what a new project has to fit into, and what tells the network team which firewall rule protects what.
A zone model that took three workshops and produced eight zones is worth more than a perfect diagram drawn in an afternoon with twenty.
References
- IEC, IEC 62443-3-2:2020, Security for industrial automation and control systems, Part 3-2: Security risk assessment for system design.
Related articles
All articles- Physical connectivity and logical segregation in OT networks: two designs, two different jobsWhich switch an asset plugs into and which security zone it belongs to are two different decisions, taken for two different reasons. One decides…
- Legacy PLCs are not going away. Shield them.The controller cannot authenticate, cannot be patched and runs a process worth more than the project that would replace it. That is not a dead end…
- IEC 62443-2-2: rating how well a zone is protected in operation, and using it in the periodic reviewThe newest part of the 62443 series asks a question most periodic reviews skip: the zone was designed to a security level, but what level does it…
EUCALEX
Have a project or a technical challenge?
Contact us: we will be pleased to discuss it with you, with no commitment.
Discuss your project with usStay informed
Receive new EUCALEX articles and technical insights by email.
